|
Case #749
$30 million provider
of leasing and maintenance on lighting service
The typical 12 months and over a million
dollars approach to implementing a new system does not
work in a turnaround situation. Instead, a critical element
of a successful turnaround is a flexible systems solution
that is implemented in weeks, not months, and at a fraction
of the cost of a typical new system.
Work for a lighting service company presented
our systems crew with some interesting challenges. Our client
was a lender that had financed a portfolio of equipment installation
and maintenance contracts that required ongoing maintenance-performance
success. Despite its $30 million in annual revenues, the company
that sold the equipment, wrote the contracts and maintained
the installed equipment was going through bankruptcy. And
now, many contracts were in jeopardy because of maintenance
performance problems.
Our crew was asked to create a new company,
which would provide the required equipment maintenance once
the lender was able to gain control of its collateral through
Bankruptcy proceeding. We had to take over the servicing of
10,000 physical locations in 40 states and to process more
than 150 requests for service daily. This operation had to
be in place within 60 to 90 days and be ready to begin handling
service requests on as little as 2 days notice.
Our analysis of this situation revealed some difficult problems
that would have to be overcome:
- The system that was used by the current
maintenance provider was outdated and no longer supported
by the software company.
- The existing system also operated on a non-supported
version of a database that was no longer available.
- The existing system was not Y2K compliant.
- The company operated three primary software
applications for its operations and each application was
an island of information.
- The existing customer, contract and service
databases (the three applications) had an extremely high
rate of duplicate and incorrect data.
Our crew looked at a number of alternatives
and found that any off the shelf software that
could handle this complex and data intensive operation
would take at least 6-12 months to implement and cost in excess
of $1 million dollars. We also found that these package systems
did not provide the tools or flexibility we needed to analyze
and cleanse the corrupt data we had to work with at the onset.
It was clear that we had to create our own solution and it
would have to have exceptional data-analysis capability, flexibility,
and be capable of being completed in less than 60 days.
The first step was a business analysis of the
operation. We identified the data and processes that were
critical to operating this business. Within a week, we had
completed the design of our new database and identified the
basic functions that our new system would have to support.
This gave us the basic blueprint for building the new system.
We also mapped future data and application needs of the business,
because we wanted the new system to be flexible and allow
us to easily add new features after we had completed the initial
startup.
We had to find a way to build and test a complete
system in less than 60 days. This would require careful selection
of the right database and software tools that would be used
to construct the new system. Most systems development efforts
take months to complete, so this project had to rely on the
use of technology that could cut that time to weeks or even
days. The success of this operation would also hinge on our
ability to analyze large volumes of data quickly to identify
problems and determine corrective strategies. In short, we
had to have a technology base that would allow us to slice
and dice data in a wide variety of ways.
Two crews immediately began the task of building this system.
Critical data elements and relationships were identified and
we began moving data into an analysis database. We constructed
tests to determine data accuracy and started the process of
cleansing the data. The first crew then built
our permanent system database and the process of data conversion
began.
A second crew began the development of the application
software. We had several objectives for the new system. First,
it would have to be very easy to use. At startup, we would
have very little time to train new employees before full operations
began, and the design would have to support a high level of
efficiency, because our goal was to run the operations with
a very limited number of staff. We also needed to have key
performance reporting from the first day. If anything were
going wrong, we would have to identify the problem immediately
and take corrective action.
The system was completed within 60 days. When
the existing maintenance provider closed their doors, we were
able to transition the operations to a totally new company
without one day of lost customer service. The
speed with which we completed the startup helped stem the
tide of contract-default notices and stabilize the customer
base (and the contract payment stream) in a very short time
period. The system has now been enhanced to a level that makes
it State of the Art for this industry, and it
has been accomplished at one-fourth the cost of off-the-shelf
alternatives.
|